Waffle roof molding time
Waffle roof molding time : Let’s check together the time of waffle roof mold removal in PSP company (manufacturer of waffle roof and waffle mold).
The molding time of the waffle roof is the same as the molding of the slabs. Because these types of structures are included in the group of concrete slab roofs, which are described in the national building regulations for molding roofs such as waffle roofs and other structural elements as follows.
Waffle roof molding time
Vertical molds need several hours to be removed. If the temperature is 0 degrees Celsius, it takes 30 hours, 8 degrees Celsius 18 hours, 16 degrees Celsius 12 hours, and finally 24 degrees Celsius or more, it takes 9 hours to be removed.
The molds can be placed below, and a specific time is defined for removing them according to the temperature. These molds are slabs. The schedule is as follows:
The beams can be placed in the molds below, and a certain temperature is needed to remove them, and the higher the temperature, the less time it takes. The table of the beams below is also defined as follows:
These features are considered among the most important points at the time of molding the waffle roof, which must be paid attention to and are vital to proceed correctly.
The reason for this time difference in opening each of these formats is various things. In the molds that are vertical, there is lateral pressure in them and no vertical pressure is seen in them. This case will cause the opening time of the templates to be earlier than other cases.
Waffle roof molding time
Comparing the slab and beam format, it can also be said that the beams have a high weight compared to the slab. For this reason, they need more time to open.
If you are planning to choose a waffle mold and a waffle roof, we are the experts and engineers of PSP (waffle roof and waffle mold manufacturer) ready to advise and cooperate with you.